Filters
Question type

Study Flashcards

The labor rate variance for October is:


A) $495 U
B) $495 F
C) $525 U
D) $525 F

E) B) and C)
F) A) and D)

Correct Answer

verifed

verified

The actual hourly rate of pay for tune-up work last week was:


A) $8.40 per hour
B) $9.00 per hour
C) $9.60 per hour
D) Cannot be computed without further information

E) None of the above
F) A) and D)

Correct Answer

verifed

verified

Todco planned to produce 3,000 units of its single product, Teragram, during November. The standard specifications for one unit of Teragram include six pounds of material at $0.30 per pound. Actual production in November was 3,100 units of Teragram. The accountant computed a favorable materials purchase price variance of $380 and an unfavorable materials quantity variance of $120. Based on these variances, one could conclude that:


A) more materials were purchased than were used.
B) more materials were used than were purchased.
C) the actual cost of materials was less than the standard cost.
D) the actual usage of materials was less than the standard alloweD.Materials price variance = AQ (AP - SP)

E) A) and C)
F) C) and D)

Correct Answer

verifed

verified

The labor rate variance for September was:


A) $1,530 unfavorable
B) $980 favorable
C) $280 favorable
D) $980 unfavorable

E) B) and C)
F) C) and D)

Correct Answer

verifed

verified

In general, the purchasing agent is responsible for the materials price variance.

A) True
B) False

Correct Answer

verifed

verified

The materials quantity variance for December is:


A) $660 F
B) $660 U
C) $627 F
D) $627 U

E) A) and B)
F) None of the above

Correct Answer

verifed

verified

The variable overhead rate variance for June is:


A) $318 U
B) $320 F
C) $318 F
D) $320 U

E) All of the above
F) C) and D)

Correct Answer

verifed

verified

The variable overhead efficiency variance for June is:


A) $185 F
B) $200 U
C) $185 U
D) $200 F

E) A) and B)
F) None of the above

Correct Answer

verifed

verified

The variable overhead efficiency variance for March is:


A) $756 U
B) $700 F
C) $756 F
D) $700 U

E) A) and B)
F) B) and C)

Correct Answer

verifed

verified

The materials quantity variance for November is:


A) $9,600 U
B) $9,760 U
C) $9,760 F
D) $9,600 F

E) A) and B)
F) All of the above

Correct Answer

verifed

verified

The materials price variance for July is:


A) $22,080 U
B) $19,950 U
C) $22,080 F
D) $19,950 F

E) B) and D)
F) B) and C)

Correct Answer

verifed

verified

The variable overhead rate variance for May is:


A) $1,440 U
B) $1,302 F
C) $1,302 U
D) $1,440 F

E) A) and C)
F) A) and B)

Correct Answer

verifed

verified

What is the materials quantity variance for the month?


A) $1,880 U
B) $10,476 U
C) $1,940 U
D) $10,152 U

E) A) and B)
F) B) and D)

Correct Answer

verifed

verified

The materials price variance for December is:


A) $710 F
B) $710 U
C) $660 F
D) $660 U

E) A) and B)
F) C) and D)

Correct Answer

verifed

verified

The variable overhead rate variance for June is:


A) $1,365 U
B) $1,365 F
C) $1,350 F
D) $1,350 U

E) B) and D)
F) B) and C)

Correct Answer

verifed

verified

The materials quantity variance for June is:


A) $392 U
B) $392 F
C) $400 F
D) $400 U

E) A) and B)
F) A) and C)

Correct Answer

verifed

verified

The following direct labor standards have been established for product E45O: The following direct labor standards have been established for product E45O:   The following data pertain to last month's operations:   Required: a. What was the labor rate variance for the month? b. What was the labor efficiency variance for the month? The following data pertain to last month's operations: The following direct labor standards have been established for product E45O:   The following data pertain to last month's operations:   Required: a. What was the labor rate variance for the month? b. What was the labor efficiency variance for the month? Required: a. What was the labor rate variance for the month? b. What was the labor efficiency variance for the month?

Correct Answer

verifed

verified

a. Labor rate variance = (AH × AR) - (AH...

View Answer

The labor efficiency variance for February is:


A) $230 F
B) $235 F
C) $230 U
D) $235 U

E) All of the above
F) A) and B)

Correct Answer

verifed

verified

The Porter Company has a standard cost system. In July the company purchased and used 22,500 pounds of direct material at an actual cost of $53,000; the materials quantity variance was $1,875 Unfavorable; and the standard quantity of materials allowed for July production was 21,750 pounds. The materials price variance for July was:


A) $2,725 F
B) $2,725 U
C) $3,250 F
D) $3,250 U

E) B) and C)
F) A) and D)

Correct Answer

verifed

verified

The following labor standards have been established for a particular product: The following labor standards have been established for a particular product:   The following data pertain to operations concerning the product for the last month:   Required: a. What is the labor rate variance for the month? b. What is the labor efficiency variance for the month? The following data pertain to operations concerning the product for the last month: The following labor standards have been established for a particular product:   The following data pertain to operations concerning the product for the last month:   Required: a. What is the labor rate variance for the month? b. What is the labor efficiency variance for the month? Required: a. What is the labor rate variance for the month? b. What is the labor efficiency variance for the month?

Correct Answer

verifed

verified

a. Labor rate variance = (AH × AR) - (AH...

View Answer

Showing 41 - 60 of 179

Related Exams

Show Answer